madlab - roof

Blood on the walls - but pretend this time

Stripping back second floor

Discovery of charred beams

Trying to work out depth of charring

The two most charred beams

Historical hole repairs

Stripped roof, prior to sandblasting

Sandblasting to remove charring to assess the amount of timber remaining to hold the roof up

The aftermath

The cleanup

Not much left of these two...

Two layers of timber work so that the new ceiling will line up with the top of the trusses

Slices of polycarbonate to ensure air gap above insulation and below underlay

Picture to show layers of insulation, staggered to remove thermal bridges

Roof insulation meets wall insulation


Hidden steelwork to stabilise purlins

Vapour control and airtightness layer being installed

Membrane glued along purlins as they are to be left exposed


Boarding out

Previously hidden roof structure now exposed for all to see

New light fittings in place


Suspended ceiling over staircase

Sapele faced ply...

to give a suitably luxurious backdrop when looking up at the staircase

Strengtheners to the two charred purlins


View through fire resisting glazing